| Client |
Project Description & Location |
Contract Duration |
Amount (RM '000)
|
| HCM -THT JV |
Design, construct, rehabilitate and upgrade of Muar -Melaka -Alor Gajah-Simpang Ampat road (70km) |
April 2001 - April 2007 |
353,934
|
| THT-HCM JV |
Chiku-Aring Kelantan 25.4 km road |
Jan 2004-August 2007 |
98,593
|
| Alloy Maintennace Engineering Sdn Bhd |
Rehabilitation of Pavement Works (Package 5A, 5B, 6A & 6B): KL-Karak Highway |
February 2005 - June 2007 |
35,550
|
| HCM -Molek JV |
Design, construct, rehabilitate and upgrade of Jalan Alor Setar-Kuala Nerang-Durian Burong, Kedah (48km) |
September 2006-September 2009 |
246,200
|
| General Company For Roads & Construction Libya (GCRB) |
Maintenance of a 238km coastal road Gharabouli -Ras Jedeir |
December 2005-November 2008 |
203,000
|
| Road & Bridges Authority, Libya (RBA) |
Design & rehabilitation of six (6) bridges at Silrt Municipality, Libya |
January 2006-October 2007 |
8,778
|
| Road & Bridges Authority, Libya (RBA) |
Maintenance of a 80km road Tripoli-Garian |
April 2007-March 2009 |
128,100
|
| JKR / HCM -MOLEK JV |
Design & rehabilitation of Jalan Alor Setar -Kuala Nerang-Durian Burong, Kedah (48km) |
September 2006 - September 2009 |
246,200
|
| Libyan Malaysian Co for Roads & Construction (LMCRC)/ HCM Arabia Sdn Bhd |
Maintenance of 80km Tripoli --Garian Road, Libya |
July 2008 - April 2009 |
113,200
|
| Dept of Roads and Bridges, Libya /HCM Arabia Sdn Bhd |
Maintenance of 88km Tarhuna-Benn Waled Road, Libya |
July 2008 - December 2009 |
78,000
|
| JKR Selangor /KPS -HCM Sdn Bhd |
Maintenance 3500km state roads in Selangor |
2008-2015 |
245,000
|
| Ministry of Education/HCM Engineering Sdn Bhd |
Teachers Training College, Penang-Phase 1 |
September 2007 - August 2008 |
10,039
|
| Kumpulan Ikram Sdn Bhd /Protasco Land Sdn Bhd |
Unipark 20- Storey Condominium (Block A) 160 Units) at Ikram Park |
April 2007 -September 2009 |
294,666
|